Southampton County, Virginia solar ordinance

Solar: 18 ft (solar energy arrays when oriented at maximum tilt) maximum height. Every figure is quoted from the county's ordinance, read September 29, 2026.

Updated September 2026

Solar rules

14 figures read from the county's ordinance, each with the sentence it comes from.

Solar rules in the Southampton County ordinance
Rule and what the ordinance saysRequirement
Setback from homessubstations or connector stationsSec. 18-627 – Substations or connector stations must be 500 feet, and inverters and transformers must be 250 feet, from existing dwellings, schools, places of worship, State Scenic Rivers, and rights-of-way.500 ft
Setback from homesinverters and transformersSec. 18-627 – Substations or connector stations must be 500 feet, and inverters and transformers must be 250 feet, from existing dwellings, schools, places of worship, State Scenic Rivers, and rights-of-way.250 ft
Road setbacksubstations or connector stationsSec. 18-627 – Substations or connector stations must be 500 feet, and inverters and transformers must be 250 feet, from existing dwellings, schools, places of worship, State Scenic Rivers, and rights-of-way.500 ft
Road setbackinverters and transformersSec. 18-627 – Substations or connector stations must be 500 feet, and inverters and transformers must be 250 feet, from existing dwellings, schools, places of worship, State Scenic Rivers, and rights-of-way.250 ft
Setback from corporate limits of any town or citySec. 18-626 – All projects must be at least one (1) mile from the corporate limits of any town or city.1 mile
Setback from schoolssubstations or connector stationsSec. 18-627 – Substations or connector stations must be 500 feet, and inverters and transformers must be 250 feet, from existing dwellings, schools, places of worship, State Scenic Rivers, and rights-of-way.500 ft
Setback from places of worshipsubstations or connector stationsSec. 18-627 – Substations or connector stations must be 500 feet, and inverters and transformers must be 250 feet, from existing dwellings, schools, places of worship, State Scenic Rivers, and rights-of-way.500 ft
Setback from State Scenic Riverssubstations or connector stationsSec. 18-627 – Substations or connector stations must be 500 feet, and inverters and transformers must be 250 feet, from existing dwellings, schools, places of worship, State Scenic Rivers, and rights-of-way.500 ft
Setback from schoolsinverters and transformersSec. 18-627 – Substations or connector stations must be 500 feet, and inverters and transformers must be 250 feet, from existing dwellings, schools, places of worship, State Scenic Rivers, and rights-of-way.250 ft
Setback from places of worshipinverters and transformersSec. 18-627 – Substations or connector stations must be 500 feet, and inverters and transformers must be 250 feet, from existing dwellings, schools, places of worship, State Scenic Rivers, and rights-of-way.250 ft
Setback from State Scenic Riversinverters and transformersSec. 18-627 – Substations or connector stations must be 500 feet, and inverters and transformers must be 250 feet, from existing dwellings, schools, places of worship, State Scenic Rivers, and rights-of-way.250 ft
Setback from other utility scale solar projectsNo project shall be closer than five (5) miles from any other such project.5 miles
Maximum heightsolar energy arrays when oriented at maximum tiltSolar Energy Arrays shall not exceed eighteen (18) feet in height when oriented at maximum tilt, as measured from the ground18 ft
Maximum project sizemaximum project sizeSec. 18-624 – The minimum project size is 20MW and the maximum size is 100MW.100 MW

Source: Southampton County ordinance (PDF), read September 29, 2026. Check the cited section with the county before relying on a figure.

More on Southampton County in Basepoint

  • Which zoning districts allow solar in Southampton County
  • Property line and road setbacks drawn on any parcel in Southampton County as its buildable area
  • Transmission, substations, parcels and environmental layers for the same site
Book a demo

Virginia state law

State law can cap or override county rules. All Virginia rules and counties.

State siting: Virginia Department of Environmental Quality; State Corporation Commission

Projects up to 150 MW can use a permit by rule from the Department of Environmental Quality. Larger ones may need a certificate from the State Corporation Commission. Local approval is also needed.

Va. Code Ann. 10.1-1197.5, 56-265.2 (DOE and Berkeley Lab inventory, June 2024). Source

Limits on local rules

For ground-mounted solar of 1 MW or more serving other property, counties must use a special exception or siting agreement whose setbacks, screening and height stay within state ranges; a county can still deny the application, and can depart from the ranges only by written agreement with the landowner and applicant.

Va. Code 15.2-2288.8(A) (2026 Acts cc. 1005, 1068). Source

Solar standards in state law

Applies to ground-mounted solar of 1 MW or more that serves other property; each county must write its special-exception rules within these ranges (picking any number inside a range), may still deny a project, and may agree looser terms in a siting agreement.

Solar standards set by Virginia law
Homes (non-participating)150 to 200 ft
Schools, churches, community buildings150 to 200 ft
Public roads50 to 100 ft from roadbed edge
Property line (non-participating)50 to 75 ft
Wetlands and perennial streams50 ft (25 MW or less), 100 ft (over 25 MW)
Wetlands and streams in Chesapeake Bay Preservation Areas100 to 125 ft
Panel height at full tilt25 ft
Screening buffer width25 to 50 ft wide; plants need not exceed 3 ft at planting
Vegetative ground coverUp to 75% may be required
DecommissioningAgreement plus financial assurance; estimate updated every 5 years

Va. Code 15.2-2288.8(A) (2026 Acts cc. 1005, 1068); 15.2-2241.2. Source

Every Virginia figure in one spreadsheet

238 figures from 32 counties, each with its quote, source, date read and any condition. 5 of those places are not on this site. Plus the moratorium or ban on file and Virginia state law.

CSV files that open in Excel or Google Sheets. No call required.

How these figures were read

We found Southampton County's own ordinance and had two AI models read it separately. A figure is shown only when both read the same number and the sentence it comes from was found in the document. Moratoria and bans are checked against the adopting document. Ordinances change and many figures apply only in some cases, so check the cited section with the county before relying on one.

Common questions

What are the solar setbacks in Southampton County, VA?

The county's ordinance sets solar facilities back 500 ft (substations or connector stations) from homes, 500 ft (substations or connector stations) from roads, 250 ft (inverters and transformers) from homes and 250 ft (inverters and transformers) from roads. Check the cited section with the county before relying on a figure.

How tall can a solar farm be in Southampton County, VA?

The ordinance sets a maximum height of 18 ft (solar energy arrays when oriented at maximum tilt). Check the cited section with the county before relying on a figure.