Charlotte County, Virginia solar ordinance

Solar: 75 ft (Utility-Scale Solar Energy Systems) from property lines, 400 ft (Utility-Scale Solar Energy Systems) from homes, 125 ft (Utility-Scale Solar Energy Systems) from roads. Every figure is quoted from the county's ordinance, read September 29, 2026.

Updated September 2026

Solar rules

8 figures read from the county's ordinance, each with the sentence it comes from.

Solar rules in the Charlotte County ordinance
Rule and what the ordinance saysRequirement
Property line setbackUtility-Scale Solar Energy Systemsa minimum setback of 75 feet from all other property lines with the exception of those property lines that are inside the project's boundaries and which do not abut property located outside the project area75 ft
Setback from homesUtility-Scale Solar Energy Systemsa minimum of 400’ from all off-site residential structures.400 ft
Road setbackUtility-Scale Solar Energy Systemsa minimum setback of 125 feet from the center line of any state maintained road abutting the property125 ft
Setback from town boundaryUtility Scale Solar Energy SystemAbsent specific authorization by the Board of Supervisors as part of a Conditional Use Permit, no Utility Scale Solar Energy System shall be located within one (1) mile of an existing town boundary.1 mile
Maximum heightground mounted Solar Energy Systems & equipmentSolar Energy Systems & equipment shall not exceed twenty-five (25) feet in height when ground mounted as measured from the highest grade at the base to the top of structure.25 ft
Fence heightUtility Scale Solar Energy SystemsUtility Scale Solar Energy Systems shall be enclosed by security fencing not less than six (6) feet in height equipped with an appropriate anti-climbing device.6 ft
Maximum project sizeland area in any given five mile radiusAbsent specific authorization by the Board of Supervisors as part of a Conditional use Permit, no more than three percent (3%) of the land area in any given five mile radius shall be approved for use as the project area for Utility-Scale Solar Energy Systems.3%
Noise limitUtility Scale Solar Energy Systems measured at property lineAfter completion of construction, noise levels measured at the property line shall not exceed 50 dbA, unless the owner of the affected adjacent property has given written agreement to a higher level.50 dBA

Source: Charlotte County ordinance (PDF), read September 29, 2026. Check the cited section with the county before relying on a figure.

More on Charlotte County in Basepoint

  • Which zoning districts allow solar in Charlotte County
  • Property line and road setbacks drawn on any parcel in Charlotte County as its buildable area
  • Transmission, substations, parcels and environmental layers for the same site
Book a demo

Virginia state law

State law can cap or override county rules. All Virginia rules and counties.

State siting: Virginia Department of Environmental Quality; State Corporation Commission

Projects up to 150 MW can use a permit by rule from the Department of Environmental Quality. Larger ones may need a certificate from the State Corporation Commission. Local approval is also needed.

Va. Code Ann. 10.1-1197.5, 56-265.2 (DOE and Berkeley Lab inventory, June 2024). Source

Limits on local rules

For ground-mounted solar of 1 MW or more serving other property, counties must use a special exception or siting agreement whose setbacks, screening and height stay within state ranges; a county can still deny the application, and can depart from the ranges only by written agreement with the landowner and applicant.

Va. Code 15.2-2288.8(A) (2026 Acts cc. 1005, 1068). Source

Solar standards in state law

Applies to ground-mounted solar of 1 MW or more that serves other property; each county must write its special-exception rules within these ranges (picking any number inside a range), may still deny a project, and may agree looser terms in a siting agreement.

Solar standards set by Virginia law
Homes (non-participating)150 to 200 ft
Schools, churches, community buildings150 to 200 ft
Public roads50 to 100 ft from roadbed edge
Property line (non-participating)50 to 75 ft
Wetlands and perennial streams50 ft (25 MW or less), 100 ft (over 25 MW)
Wetlands and streams in Chesapeake Bay Preservation Areas100 to 125 ft
Panel height at full tilt25 ft
Screening buffer width25 to 50 ft wide; plants need not exceed 3 ft at planting
Vegetative ground coverUp to 75% may be required
DecommissioningAgreement plus financial assurance; estimate updated every 5 years

Va. Code 15.2-2288.8(A) (2026 Acts cc. 1005, 1068); 15.2-2241.2. Source

Every Virginia figure in one spreadsheet

238 figures from 32 counties, each with its quote, source, date read and any condition. 5 of those places are not on this site. Plus the moratorium or ban on file and Virginia state law.

CSV files that open in Excel or Google Sheets. No call required.

How these figures were read

We found Charlotte County's own ordinance and had two AI models read it separately. A figure is shown only when both read the same number and the sentence it comes from was found in the document. Moratoria and bans are checked against the adopting document. Ordinances change and many figures apply only in some cases, so check the cited section with the county before relying on one.

Common questions

What are the solar setbacks in Charlotte County, VA?

The county's ordinance sets solar facilities back 125 ft (Utility-Scale Solar Energy Systems) from roads, 75 ft (Utility-Scale Solar Energy Systems) from property lines and 400 ft (Utility-Scale Solar Energy Systems) from homes. Check the cited section with the county before relying on a figure.

How tall can a solar farm be in Charlotte County, VA?

The ordinance sets a maximum height of 25 ft (ground mounted Solar Energy Systems & equipment). Check the cited section with the county before relying on a figure.