Washington County, Virginia solar ordinance

Solar: 50 ft (non-participating property) from property lines, 100 ft (inhabitant residence) from homes, 100 ft from roads. Every figure is quoted from the county's ordinance, read September 30, 2026.

Updated September 2026

Solar rules

6 figures read from the county's ordinance, each with the sentence it comes from.

Solar rules in the Washington County ordinance
Rule and what the ordinance saysRequirement
Property line setbacknon-participating propertythe perimeter of the system shall be located at least fifty (50) feet from the property line of any adjoining parcel owned by any landowner other than the owner of the parcel on which the solar facility is being proposed50 ft
Setback from homesinhabitant residenceat least one hundred (100) feet from the nearest inhabitant residence at the time of the initial application100 ft
Road setbackat least one hundred (100) feet from the nearest road.100 ft
Maximum heightthe height of the structures and arrays in the system shall be ground mounted and not exceed fifteen (15) feet as measured from grade at the base of the structure to the apex of the structure15 ft
Fence heightminimumThe solar facility shall be enclosed around the perimeter by a security fence with a minimum height of six (6) feet with an appropriate anti-climbing device.6 ft
Noise limitInverter noise shall not exceed fifty (50) dBA, measured at the facility property line.50 dBA

Source: Washington County ordinance (PDF), read September 30, 2026. Check the cited section with the county before relying on a figure.

More on Washington County in Basepoint

  • Which zoning districts allow solar in Washington County
  • Property line and road setbacks drawn on any parcel in Washington County as its buildable area
  • Transmission, substations, parcels and environmental layers for the same site
Book a demo

Virginia state law

State law can cap or override county rules. All Virginia rules and counties.

State siting: Virginia Department of Environmental Quality; State Corporation Commission

Projects up to 150 MW can use a permit by rule from the Department of Environmental Quality. Larger ones may need a certificate from the State Corporation Commission. Local approval is also needed.

Va. Code Ann. 10.1-1197.5, 56-265.2 (DOE and Berkeley Lab inventory, June 2024). Source

Limits on local rules

For ground-mounted solar of 1 MW or more serving other property, counties must use a special exception or siting agreement whose setbacks, screening and height stay within state ranges; a county can still deny the application, and can depart from the ranges only by written agreement with the landowner and applicant.

Va. Code 15.2-2288.8(A) (2026 Acts cc. 1005, 1068). Source

Solar standards in state law

Applies to ground-mounted solar of 1 MW or more that serves other property; each county must write its special-exception rules within these ranges (picking any number inside a range), may still deny a project, and may agree looser terms in a siting agreement.

Solar standards set by Virginia law
Homes (non-participating)150 to 200 ft
Schools, churches, community buildings150 to 200 ft
Public roads50 to 100 ft from roadbed edge
Property line (non-participating)50 to 75 ft
Wetlands and perennial streams50 ft (25 MW or less), 100 ft (over 25 MW)
Wetlands and streams in Chesapeake Bay Preservation Areas100 to 125 ft
Panel height at full tilt25 ft
Screening buffer width25 to 50 ft wide; plants need not exceed 3 ft at planting
Vegetative ground coverUp to 75% may be required
DecommissioningAgreement plus financial assurance; estimate updated every 5 years

Va. Code 15.2-2288.8(A) (2026 Acts cc. 1005, 1068); 15.2-2241.2. Source

Every Virginia figure in one spreadsheet

238 figures from 32 counties, each with its quote, source, date read and any condition. 5 of those places are not on this site. Plus the moratorium or ban on file and Virginia state law.

CSV files that open in Excel or Google Sheets. No call required.

How these figures were read

We found Washington County's own ordinance and had two AI models read it separately. A figure is shown only when both read the same number and the sentence it comes from was found in the document. Moratoria and bans are checked against the adopting document. Ordinances change and many figures apply only in some cases, so check the cited section with the county before relying on one.

Common questions

What are the solar setbacks in Washington County, VA?

The county's ordinance sets solar facilities back 50 ft (non-participating property) from property lines, 100 ft (inhabitant residence) from homes and 100 ft from roads. Check the cited section with the county before relying on a figure.

How tall can a solar farm be in Washington County, VA?

The ordinance sets a maximum height of 15 ft. Check the cited section with the county before relying on a figure.