Sussex County, Virginia solar ordinance

Solar: 150 ft (utility-scale solar facility) from property lines, 300 ft (utility-scale solar facility) from homes, 150 ft (utility-scale solar facility) from roads. Every figure is quoted from the county's ordinance, read September 30, 2026.

Updated September 2026

Solar rules

9 figures read from the county's ordinance, each with the sentence it comes from.

Solar rules in the Sussex County ordinance
Rule and what the ordinance saysRequirement
Property line setbackutility-scale solar facilitya. 150 feet from adjacent property lines.150 ft
Setback from homesutility-scale solar facilityc. 300 feet from a dwelling.300 ft
Road setbackutility-scale solar facilityb. 150 feet from all public rights-of-way.150 ft
Maximum heightlowest edge of photovoltaic panelsThe maximum height of the lowest edge of photovoltaic panels shall be ten feet as measured from the finished grade.10 ft
Maximum heighthighest edge of photovoltaic panelsThe maximum height of the highest edge of photovoltaic panels shall not exceed 15 feet as measured from the finished grade.15 ft
Maximum heightother facility structuresThe maximum height of other facility structures shall not exceed 15 feet.15 ft
Fence heightThe facilities shall be enclosed by security fencing not less than six feet in height and topped with barbed wire, as appropriate.6 ft
Minimum lot sizeutility-scale solar facilityThe minimum area of a utility-scale solar facility shall be 100 acres or more.100 acres
Maximum lot coverageutility-scale solar facilityIn no case shall any utility-scale facility have a maximum coverage area more than 65 percent in accordance with section 34-910(b)(2).65%

Source: Sussex County ordinance (PDF), read September 30, 2026. Check the cited section with the county before relying on a figure.

More on Sussex County in Basepoint

  • Which zoning districts allow solar in Sussex County
  • Property line and road setbacks drawn on any parcel in Sussex County as its buildable area
  • Transmission, substations, parcels and environmental layers for the same site
Book a demo

Virginia state law

State law can cap or override county rules. All Virginia rules and counties.

State siting: Virginia Department of Environmental Quality; State Corporation Commission

Projects up to 150 MW can use a permit by rule from the Department of Environmental Quality. Larger ones may need a certificate from the State Corporation Commission. Local approval is also needed.

Va. Code Ann. 10.1-1197.5, 56-265.2 (DOE and Berkeley Lab inventory, June 2024). Source

Limits on local rules

For ground-mounted solar of 1 MW or more serving other property, counties must use a special exception or siting agreement whose setbacks, screening and height stay within state ranges; a county can still deny the application, and can depart from the ranges only by written agreement with the landowner and applicant.

Va. Code 15.2-2288.8(A) (2026 Acts cc. 1005, 1068). Source

Solar standards in state law

Applies to ground-mounted solar of 1 MW or more that serves other property; each county must write its special-exception rules within these ranges (picking any number inside a range), may still deny a project, and may agree looser terms in a siting agreement.

Solar standards set by Virginia law
Homes (non-participating)150 to 200 ft
Schools, churches, community buildings150 to 200 ft
Public roads50 to 100 ft from roadbed edge
Property line (non-participating)50 to 75 ft
Wetlands and perennial streams50 ft (25 MW or less), 100 ft (over 25 MW)
Wetlands and streams in Chesapeake Bay Preservation Areas100 to 125 ft
Panel height at full tilt25 ft
Screening buffer width25 to 50 ft wide; plants need not exceed 3 ft at planting
Vegetative ground coverUp to 75% may be required
DecommissioningAgreement plus financial assurance; estimate updated every 5 years

Va. Code 15.2-2288.8(A) (2026 Acts cc. 1005, 1068); 15.2-2241.2. Source

Every Virginia figure in one spreadsheet

238 figures from 32 counties, each with its quote, source, date read and any condition. 5 of those places are not on this site. Plus the moratorium or ban on file and Virginia state law.

CSV files that open in Excel or Google Sheets. No call required.

How these figures were read

We found Sussex County's own ordinance and had two AI models read it separately. A figure is shown only when both read the same number and the sentence it comes from was found in the document. Moratoria and bans are checked against the adopting document. Ordinances change and many figures apply only in some cases, so check the cited section with the county before relying on one.

Common questions

What are the solar setbacks in Sussex County, VA?

The county's ordinance sets solar facilities back 150 ft (utility-scale solar facility) from property lines, 150 ft (utility-scale solar facility) from roads and 300 ft (utility-scale solar facility) from homes. Check the cited section with the county before relying on a figure.

How tall can a solar farm be in Sussex County, VA?

The ordinance sets a maximum height of 10 ft (lowest edge of photovoltaic panels), 15 ft (highest edge of photovoltaic panels) and 15 ft (other facility structures). Check the cited section with the county before relying on a figure.

What is the minimum lot size for a solar farm in Sussex County, VA?

The ordinance sets a minimum lot size of 100 acres (utility-scale solar facility). Check the cited section with the county before relying on a figure.