King George County, Virginia solar ordinance

Solar: 15 ft (ground-mounted utility-scale solar) maximum height, 2 acres (utility-scale solar) minimum lot, 65 dBA (measured at the property line) noise limit. Every figure is quoted from the county's ordinance, read September 29, 2026.

Updated September 2026

Solar rules

9 figures read from the county's ordinance, each with the sentence it comes from.

Solar rules in the King George County ordinance
Rule and what the ordinance saysRequirement
Setback from residential district, planned development district, or dwellingutility-scale solar(ii) All structures - including fences, panels, and all ancillary equipment/buildings – shall be at least 200 ft. from any residential district, planned development district, or dwelling;200 ft
Setback from agricultural, commercial, or industrial districtutility-scale solar(iii) All structures - including fences, panels, and all ancillary equipment/buildings – shall be at least 100 ft. from all agricultural, commercial, or industrial district.100 ft
Maximum heightground-mounted utility-scale solar(1) If the utility-scale solar energy facility is ground-mounted, the facility’s height shall not exceed 15 ft. at the tallest point, including appurtenances.15 ft
Fence heightutility-scale solar(1) All security fencing shall be a minimum of 6 ft. in height and topped with razor/barbed wire, as appropriate.6 ft
Minimum lot sizeutility-scale solar(F) Lot Area. Minimum lot area of 2 acres, and the maximum area shall be 500 acres, including the required open space.2 acres
Maximum lot coverageutility-scale solar(G) Lot Coverage . Lot coverage shall not exceed 65% of the total lot acreage, including the space between panels.65%
Maximum project sizeutility-scale solar(F) Lot Area. Minimum lot area of 2 acres, and the maximum area shall be 500 acres, including the required open space.500 acres
Noise limitmeasured at the property line(M) Noise. During operation, a utility-scale solar facility shall not produce a noise level that exceeds 65 dBA as measured at the property line or 50 dBA as measured at the nearest neighboring dwelling.65 dBA
Noise limitmeasured at the nearest neighboring dwelling(M) Noise. During operation, a utility-scale solar facility shall not produce a noise level that exceeds 65 dBA as measured at the property line or 50 dBA as measured at the nearest neighboring dwelling.50 dBA

Source: King George County ordinance (PDF), read September 29, 2026. Check the cited section with the county before relying on a figure.

More on King George County in Basepoint

  • Which zoning districts allow solar in King George County
  • Transmission, substations, parcels and environmental layers for the same site
Book a demo

Virginia state law

State law can cap or override county rules. All Virginia rules and counties.

State siting: Virginia Department of Environmental Quality; State Corporation Commission

Projects up to 150 MW can use a permit by rule from the Department of Environmental Quality. Larger ones may need a certificate from the State Corporation Commission. Local approval is also needed.

Va. Code Ann. 10.1-1197.5, 56-265.2 (DOE and Berkeley Lab inventory, June 2024). Source

Limits on local rules

For ground-mounted solar of 1 MW or more serving other property, counties must use a special exception or siting agreement whose setbacks, screening and height stay within state ranges; a county can still deny the application, and can depart from the ranges only by written agreement with the landowner and applicant.

Va. Code 15.2-2288.8(A) (2026 Acts cc. 1005, 1068). Source

Solar standards in state law

Applies to ground-mounted solar of 1 MW or more that serves other property; each county must write its special-exception rules within these ranges (picking any number inside a range), may still deny a project, and may agree looser terms in a siting agreement.

Solar standards set by Virginia law
Homes (non-participating)150 to 200 ft
Schools, churches, community buildings150 to 200 ft
Public roads50 to 100 ft from roadbed edge
Property line (non-participating)50 to 75 ft
Wetlands and perennial streams50 ft (25 MW or less), 100 ft (over 25 MW)
Wetlands and streams in Chesapeake Bay Preservation Areas100 to 125 ft
Panel height at full tilt25 ft
Screening buffer width25 to 50 ft wide; plants need not exceed 3 ft at planting
Vegetative ground coverUp to 75% may be required
DecommissioningAgreement plus financial assurance; estimate updated every 5 years

Va. Code 15.2-2288.8(A) (2026 Acts cc. 1005, 1068); 15.2-2241.2. Source

Every Virginia figure in one spreadsheet

238 figures from 32 counties, each with its quote, source, date read and any condition. 5 of those places are not on this site. Plus the moratorium or ban on file and Virginia state law.

CSV files that open in Excel or Google Sheets. No call required.

How these figures were read

We found King George County's own ordinance and had two AI models read it separately. A figure is shown only when both read the same number and the sentence it comes from was found in the document. Moratoria and bans are checked against the adopting document. Ordinances change and many figures apply only in some cases, so check the cited section with the county before relying on one.

Common questions

How tall can a solar farm be in King George County, VA?

The ordinance sets a maximum height of 15 ft (ground-mounted utility-scale solar). Check the cited section with the county before relying on a figure.

What is the minimum lot size for a solar farm in King George County, VA?

The ordinance sets a minimum lot size of 2 acres (utility-scale solar). Check the cited section with the county before relying on a figure.