Page County, Virginia solar ordinance

Solar: 2 acres (utility-scale solar facility) minimum lot. Every figure is quoted from the county's ordinance, read September 30, 2026.

Updated September 2026

Solar rules

11 figures read from the county's ordinance, each with the sentence it comes from.

Solar rules in the Page County ordinance
Rule and what the ordinance saysRequirement
Setback from town boundaryutility-scale solar facilityBe located at least one (1) mile from a town boundary;1 mile
Setback from other utility-scale solar facilityunless the combined acreage coverage is thirty (30) acres or lessNot be located within two (2) miles of another existing or permitted industrial/utility scale solar facility, unless the combined acreage coverage is thirty (30) acres or less.2 miles
Setback from electric transmission linesconnection pointLocate the point of connection to the utility within one (1) mile of electric transmission lines.1 mile
Setback from historic and cultural resourcesutility-scale solar facilityNot be located in or within three hundred (300) feet of historic and cultural resources as defined in the Comprehensive Plan.300 ft
Maximum heightlowest edge of photovoltaic panelsThe maximum height of the lowest edge of the photovoltaic panels shall be 10 feet as measured from the finished grade.10 ft
Maximum heightphotovoltaic panels, primary structures, battery storage systems and accessory buildingsThe maximum height of photovoltaic panels, primary structures, battery storage systems and accessory buildings shall be 15 feet as measured from the finished grade at the base of the structure to its highest point, including appurtenances.15 ft
Fence heightutility-scale solar facility security fencingUtility-scale solar facilities shall be enclosed by security fencing on the interior of the buffer area (not to be seen by other properties) not less than nine (9) feet in height.9 ft
Minimum lot sizeutility-scale solar facilityThe minimum area of a utility-scale solar facility shall be two (2) acres.2 acres
Maximum lot coverageutility-scale solar facilityThe percent of acreage coverage shall not exceed sixty-five percent (65%) of the project site.65%
Maximum project sizeaggregate capCommencing on [effective date], and continuing until amended by the Board of Supervisors, no more than three hundred (300) acres of acreage coverage, in aggregate, may be approved for utility-scale solar facilities.300 acres
Maximum project sizeindividual utility-scale solar facilityNo more than thirty (30) acres of acreage coverage may be approved for an individual utility-scale solar facility.30 acres

Source: Page County ordinance (PDF), read September 30, 2026. Check the cited section with the county before relying on a figure.

More on Page County in Basepoint

  • Which zoning districts allow solar in Page County
  • Transmission, substations, parcels and environmental layers for the same site
Book a demo

Virginia state law

State law can cap or override county rules. All Virginia rules and counties.

State siting: Virginia Department of Environmental Quality; State Corporation Commission

Projects up to 150 MW can use a permit by rule from the Department of Environmental Quality. Larger ones may need a certificate from the State Corporation Commission. Local approval is also needed.

Va. Code Ann. 10.1-1197.5, 56-265.2 (DOE and Berkeley Lab inventory, June 2024). Source

Limits on local rules

For ground-mounted solar of 1 MW or more serving other property, counties must use a special exception or siting agreement whose setbacks, screening and height stay within state ranges; a county can still deny the application, and can depart from the ranges only by written agreement with the landowner and applicant.

Va. Code 15.2-2288.8(A) (2026 Acts cc. 1005, 1068). Source

Solar standards in state law

Applies to ground-mounted solar of 1 MW or more that serves other property; each county must write its special-exception rules within these ranges (picking any number inside a range), may still deny a project, and may agree looser terms in a siting agreement.

Solar standards set by Virginia law
Homes (non-participating)150 to 200 ft
Schools, churches, community buildings150 to 200 ft
Public roads50 to 100 ft from roadbed edge
Property line (non-participating)50 to 75 ft
Wetlands and perennial streams50 ft (25 MW or less), 100 ft (over 25 MW)
Wetlands and streams in Chesapeake Bay Preservation Areas100 to 125 ft
Panel height at full tilt25 ft
Screening buffer width25 to 50 ft wide; plants need not exceed 3 ft at planting
Vegetative ground coverUp to 75% may be required
DecommissioningAgreement plus financial assurance; estimate updated every 5 years

Va. Code 15.2-2288.8(A) (2026 Acts cc. 1005, 1068); 15.2-2241.2. Source

Every Virginia figure in one spreadsheet

238 figures from 32 counties, each with its quote, source, date read and any condition. 5 of those places are not on this site. Plus the moratorium or ban on file and Virginia state law.

CSV files that open in Excel or Google Sheets. No call required.

How these figures were read

We found Page County's own ordinance and had two AI models read it separately. A figure is shown only when both read the same number and the sentence it comes from was found in the document. Moratoria and bans are checked against the adopting document. Ordinances change and many figures apply only in some cases, so check the cited section with the county before relying on one.

Common questions

How tall can a solar farm be in Page County, VA?

The ordinance sets a maximum height of 10 ft (lowest edge of photovoltaic panels) and 15 ft (photovoltaic panels, primary structures, battery storage systems and accessory buildings). Check the cited section with the county before relying on a figure.

What is the minimum lot size for a solar farm in Page County, VA?

The ordinance sets a minimum lot size of 2 acres (utility-scale solar facility). Check the cited section with the county before relying on a figure.