Solar: 150 ft from property lines, 250 ft from homes, 150 ft from roads. Every figure is quoted from the county's ordinance, read September 30, 2026.

Updated September 2026

Solar rules

14 figures read from the county's ordinance, each with the sentence it comes from.

Solar rules in the Grayson County ordinance
Rule and what the ordinance saysRequirement
Property line setbacka. 150 feet from adjacent property lines.150 ft
Setback from homesc. 250 feet from a dwelling.250 ft
Road setbackb. 150 feet from all public rights-of-way.150 ft
Setback from town or city boundariesiii. Solar facilities shall not be located closer than 1 mile to any town or city boundaries, or from properties in the Rural Residence (RR), Highland/Recreation-Public (HR-P), or Shoreline Recreation (SR) zoning districts.1 mile
Setback from Rural Residence (RR) zoning districtiii. Solar facilities shall not be located closer than 1 mile to any town or city boundaries, or from properties in the Rural Residence (RR), Highland/Recreation-Public (HR-P), or Shoreline Recreation (SR) zoning districts.1 mile
Setback from existing or permitted large-scale solar facilityiv. No solar facility shall be located within 2 miles of another existing or permitted large-scale solar facility.2 miles
Setback from transmission line corridorsfacilities interconnecting to transmission linesv. Solar facilities interconnecting to transmission lines shall be located within 2 miles of transmission line corridors.2 miles
Maximum heightlowest edge of photovoltaic panels measured from finished gradethe maximum height of the lowest edge of photovoltaic panels shall be 10 feet as measured from the finished grade.10 ft
Maximum heightpanels, buildings, structures and other components measured from highest natural gradeThe maximum height of panels, buildings, structures and other components of a solar facility shall be 15 feet, which shall be measured from the highest natural grade below each element.15 ft
Fence heightminimum security fencing heightenclosed by security fencing on the interior of the buffer area (not to be seen by other properties) at a minimum of 7 feet in height7 ft
Maximum lot coveragearea of solar panel coverage for any single solar facility projectii. The area of solar panel coverage for any single solar facility project may not exceed 65 percent of the total acreage of the project.65%
Maximum lot coveragefenced area in any given 5-mile radiusno more than 3 percent of the land area in any given 5-mile radius shall be approved for use as the fenced area for a large-scale solar facility.3%
Maximum project sizemaximum project areai. The maximum project area of a solar facility shall be 500 acres.500 acres
Noise limitAudible sound from solar facilities shall not exceed sixty (60) decibels, as measured from any adjacent non-participating landowners' property line.60 dBA

Source: Grayson County ordinance (PDF), read September 30, 2026. Check the cited section with the county before relying on a figure.

More on Grayson County in Basepoint

  • Which zoning districts allow solar in Grayson County
  • Property line and road setbacks drawn on any parcel in Grayson County as its buildable area
  • Transmission, substations, parcels and environmental layers for the same site
Book a demo

Virginia state law

State law can cap or override county rules. All Virginia rules and counties.

State siting: Virginia Department of Environmental Quality; State Corporation Commission

Projects up to 150 MW can use a permit by rule from the Department of Environmental Quality. Larger ones may need a certificate from the State Corporation Commission. Local approval is also needed.

Va. Code Ann. 10.1-1197.5, 56-265.2 (DOE and Berkeley Lab inventory, June 2024). Source

Limits on local rules

For ground-mounted solar of 1 MW or more serving other property, counties must use a special exception or siting agreement whose setbacks, screening and height stay within state ranges; a county can still deny the application, and can depart from the ranges only by written agreement with the landowner and applicant.

Va. Code 15.2-2288.8(A) (2026 Acts cc. 1005, 1068). Source

Solar standards in state law

Applies to ground-mounted solar of 1 MW or more that serves other property; each county must write its special-exception rules within these ranges (picking any number inside a range), may still deny a project, and may agree looser terms in a siting agreement.

Solar standards set by Virginia law
Homes (non-participating)150 to 200 ft
Schools, churches, community buildings150 to 200 ft
Public roads50 to 100 ft from roadbed edge
Property line (non-participating)50 to 75 ft
Wetlands and perennial streams50 ft (25 MW or less), 100 ft (over 25 MW)
Wetlands and streams in Chesapeake Bay Preservation Areas100 to 125 ft
Panel height at full tilt25 ft
Screening buffer width25 to 50 ft wide; plants need not exceed 3 ft at planting
Vegetative ground coverUp to 75% may be required
DecommissioningAgreement plus financial assurance; estimate updated every 5 years

Va. Code 15.2-2288.8(A) (2026 Acts cc. 1005, 1068); 15.2-2241.2. Source

Every Virginia figure in one spreadsheet

238 figures from 32 counties, each with its quote, source, date read and any condition. 5 of those places are not on this site. Plus the moratorium or ban on file and Virginia state law.

CSV files that open in Excel or Google Sheets. No call required.

How these figures were read

We found Grayson County's own ordinance and had two AI models read it separately. A figure is shown only when both read the same number and the sentence it comes from was found in the document. Moratoria and bans are checked against the adopting document. Ordinances change and many figures apply only in some cases, so check the cited section with the county before relying on one.

Common questions

What are the solar setbacks in Grayson County, VA?

The county's ordinance sets solar facilities back 150 ft from property lines, 150 ft from roads and 250 ft from homes. Check the cited section with the county before relying on a figure.

How tall can a solar farm be in Grayson County, VA?

The ordinance sets a maximum height of 10 ft (lowest edge of photovoltaic panels measured from finished grade) and 15 ft (panels, buildings, structures and other components measured from highest natural grade). Check the cited section with the county before relying on a figure.