Butler County, Nebraska solar, wind and battery storage moratorium

Butler County adopted a moratorium on March 16, 2026, and we could not confirm it is still in force. It covers commercial solar and wind farms, and battery storage (also data centers and landfills).

Updated September 2026

Moratorium

Moratorium, current status not confirmed

Commercial solar and wind farms, and battery storage (also data centers and landfills)

Adopted
March 16, 2026
Runs to
No end date found
Scope
Butler County Solar (Sandhills Energy) project exempted by Resolution 2026-11 on 2026-04-06
Checked
September 29, 2026
Supervisor Griess said he reviewed the community survey results and noted definite support for the top five land uses (wind, solar, data centers, battery storage, landfill).

Adopting document

More on Butler County in Basepoint

  • Moratoria and local rules flagged on the parcels you screen
  • Transmission, substations, parcels and environmental layers for the same site
Book a demo

Nebraska state law

State law can cap or override county rules. All Nebraska rules and counties.

State siting: Nebraska Power Review Board

New generation needs Power Review Board approval, but privately developed renewable projects are exempt if they file a request with the board before building.

Neb. Rev. Stat. 70-1012, 70-1014.02 (DOE and Berkeley Lab inventory, June 2024). Source

Every Nebraska figure in one spreadsheet

189 figures from 23 counties, each with its quote, source, date read and any condition. 1 of those places is not on this site. Plus the 8 moratoria and bans on file and Nebraska state law.

CSV files that open in Excel or Google Sheets. No call required.

How these figures were read

Moratoria and bans are checked against the adopting document. Ordinances change and many figures apply only in some cases, so check the cited section with the county before relying on one.

Common questions

Is there a solar, wind and battery storage moratorium in Butler County, NE?

Butler County adopted a moratorium on March 16, 2026, and we could not confirm it is still in force. It covers commercial solar and wind farms, and battery storage (also data centers and landfills). Checked against the adopting document on September 29, 2026.