Solar: 200 ft (Large Solar Energy Systems) from homes. Wind: 125% (Commercial WECS) decommissioning bond. Every figure is quoted from the county's ordinance, read October 7, 2026.

Updated October 2026

Solar rules

3 figures read from the county's ordinance, each with the sentence it comes from.

Solar rules in the Faribault County ordinance
Rule and what the ordinance saysRequirement
Setback from homesLarge Solar Energy SystemsLarge Solar Energy Systems must meet the minimum building setback for the zoning district and be located a minimum of two hundred (200) feet from a residential dwelling unit not located on the property.200 ft
Setback from Drainage SystemsLarge Solar Energy SystemsLarge Solar Energy Systems must meet a minimum setback of 100 feet from Dr ainage Systems.100 ft
Decommissioning bondLarge Solar Energy SystemsThe B oard shall require an escrow account or surety bond equal to one hundred twenty-five (125) percent of the costs to ensure proper decommissioning.125%

Source: Faribault County ordinance (PDF), read October 7, 2026. Check the cited section with the county before relying on a figure.

Wind rules

1 figure read from the county's ordinance, each with the sentence it comes from.

Wind rules in the Faribault County ordinance
Rule and what the ordinance saysRequirement
Decommissioning bondCommercial WECSThe Board shall require an escrow account or surety bond equal to one hundred twenty-five (125) percent of the costs to ensure proper decommissioning.125%

Source: Faribault County ordinance (PDF), read October 7, 2026. Check the cited section with the county before relying on a figure.

More on Faribault County in Basepoint

  • Which zoning districts allow solar in Faribault County
  • Transmission, substations, parcels and environmental layers for the same site
Book a demo

Minnesota state law

State law can cap or override county rules. All Minnesota rules and counties.

State siting: Minnesota Public Utilities Commission

A state site permit is needed for solar of 50 MW or more, wind of 5 MW or more and storage of 10 MW or more; the developer may instead seek local approval for solar under 80 MW, wind under 25 MW and any storage.

Minn. Stat. 216I.02 subd. 6, 11, 17, 18; 216I.08; 216I.10 (2024 permitting reform). Source

Limits on local rules

A state site permit overrides county and town zoning for projects of 50 MW or more; no limit was found for smaller projects.

Minn. Stat. 216I.18. Source

Solar standards in state law

Statewide noise limits apply to every noise source, so they bind solar arrays whether the state or a county permits it; no statewide setback figures were found.

Solar standards set by Minnesota law
Noise50 dBA L50 night, 60 dBA L50 day (residential)

Minn. R. 7030.0040. Source

Wind standards in state law

Statewide noise limits apply to every noise source, so they bind wind turbines whether the state or a county permits it; no statewide setback figures were found.

Wind standards set by Minnesota law
Noise50 dBA L50 night, 60 dBA L50 day (residential)

Minn. R. 7030.0040. Source

Every Minnesota figure in one spreadsheet

158 figures from 30 counties, each with its quote, source, date read and any condition. 10 of those places are not on this site. Plus the 2 moratoria and bans on file and Minnesota state law.

CSV files that open in Excel or Google Sheets. No call required.

How these figures were read

We found Faribault County's own ordinance and had two AI models read it separately. A figure is shown only when both read the same number and the sentence it comes from was found in the document. Moratoria and bans are checked against the adopting document. Ordinances change and many figures apply only in some cases, so check the cited section with the county before relying on one.

Common questions

What are the solar setbacks in Faribault County, MN?

The county's ordinance sets solar facilities back 200 ft (Large Solar Energy Systems) from homes. Check the cited section with the county before relying on a figure.