Teller County, Colorado solar and battery storage moratorium

Teller County has a moratorium in force since June 9, 2026, with no end date found. It covers solar energy collection and battery storage, and other major utility projects (electricity generation/transmission/storage, geothermal, nuclear, data centers).

Updated September 2026

Moratorium

Moratorium in force

Solar energy collection and battery storage, and other major utility projects (electricity generation/transmission/storage, geothermal, nuclear, data centers)

Adopted
June 9, 2026
Runs to
No end date found
Scope
the Teller County Wastewater Utility expansion; unincorporated county only
Checked
September 29, 2026
any applications for major utility projects, including but not limited to, facilities of the generation, transmission or storage of electricity, commercial battery energy storage, solar energy collection, and/or geothermal resources, nuclear power plants, and data centers.

Adopting document

More on Teller County in Basepoint

  • Moratoria and local rules flagged on the parcels you screen
  • Transmission, substations, parcels and environmental layers for the same site
Book a demo

Colorado state law

State law can cap or override county rules. All Colorado rules and counties.

Limits on local rules

For public utilities and power authorities only, local governments must decide within set deadlines and a denial can be appealed to the Public Utilities Commission.

C.R.S. 29-20-108. Source

Every Colorado figure in one spreadsheet

79 figures from 19 counties, each with its quote, source, date read and any condition. 8 of those places are not on this site. Plus the 3 moratoria and bans on file and Colorado state law.

CSV files that open in Excel or Google Sheets. No call required.

How these figures were read

Moratoria and bans are checked against the adopting document. Ordinances change and many figures apply only in some cases, so check the cited section with the county before relying on one.

Common questions

Is there a solar and battery storage moratorium in Teller County, CO?

Teller County has a moratorium in force since June 9, 2026, with no end date found. It covers solar energy collection and battery storage, and other major utility projects (electricity generation/transmission/storage, geothermal, nuclear, data centers). Checked against the adopting document on September 29, 2026.