Sweetwater County, Wyoming solar and wind ordinance

Solar: 50 ft from property lines, 200 ft (properties zoned agriculture) from roads, 25 ft (Solar Energy Facility structures) maximum height. Wind: 45 dBA (between 7 am and 7 pm MDT) noise limit. Every figure is quoted from the county's ordinance, read September 30, 2026.

Updated September 2026

Solar rules

8 figures read from the county's ordinance, each with the sentence it comes from.

Solar rules in the Sweetwater County ordinance
Rule and what the ordinance saysRequirement
Property line setback(13) Setbacks. Solar Energy Facility structures shall be setback from all property lines at least fifty feet.50 ft
Road setbackproperties zoned agricultureAll Solar Energy Facility structures shall be setback not less than two hundred feet from public rights - of - way for properties zoned agriculture200 ft
Road setbackon all other lands allowedand one hundred feet on all other lands allowed by this Resolution100 ft
Setback from residentially zoned properties or residenceSolar Energy Facility structures shall be setback a minimum of 1.25 miles from any residentially zoned properties or residence.1.25 miles
Maximum heightSolar Energy Facility structures(4) Height. All Solar Energy Facilities structures shall not exceed twenty five feet in height.25 ft
Minimum lot size(6) Minimum lot size. No Solar Energy Facility shall be constructed on any parcel less than 40 acres in size.40 acres
Noise limitbetween 7 AM and 7 PM MDT at the property line of any neighboring residentially zoned loti. 50 decibels on the dB(A) scale during the hours between 7 AM and 7 PM MDT as measured at the property line of any neighboring residentially zoned lot50 dBA
Noise limitbetween 7 PM and 7 AM MDT at the property line of any neighboring residentially zoned lotii. 45 decibels on the dB(A) scale during the hours between 7 PM and 7 AM MDT as measured at the property line of any neighboring residentially zoned lot.45 dBA

Source: Sweetwater County ordinance (PDF), read September 30, 2026. Check the cited section with the county before relying on a figure.

Wind rules

2 figures read from the county's ordinance, each with the sentence it comes from.

Wind rules in the Sweetwater County ordinance
Rule and what the ordinance saysRequirement
Noise limitbetween 7 am and 7 pm MDT1. 45 decibels on the dB(A) scale during the hours between 7 am and 7 pm MDT, and45 dBA
Noise limitbetween 7 pm and 7 am MDT2. 40 decibels on the dB(A) scale during the hours between 7 pm and 7 am MDT.40 dBA

Source: Sweetwater County ordinance (PDF), read September 30, 2026. Check the cited section with the county before relying on a figure.

More on Sweetwater County in Basepoint

  • Which zoning districts allow solar in Sweetwater County
  • Property line and road setbacks drawn on any parcel in Sweetwater County as its buildable area
  • Transmission, substations, parcels and environmental layers for the same site
Book a demo

Wyoming state law

State law can cap or override county rules. All Wyoming rules and counties.

State siting: Wyoming Industrial Siting Council

Solar larger than 30 MW, or disturbing 100 acres or more, needs a state permit as well as a county permit.

Wyo. Stat. 35-12-102, 35-12-106 (DOE and Berkeley Lab inventory, June 2024). Source

Every Wyoming figure in one spreadsheet

50 figures from 8 counties, each with its quote, source, date read and any condition. 2 of those places are not on this site. Plus Wyoming state law.

CSV files that open in Excel or Google Sheets. No call required.

How these figures were read

We found Sweetwater County's own ordinance and had two AI models read it separately. A figure is shown only when both read the same number and the sentence it comes from was found in the document. Moratoria and bans are checked against the adopting document. Ordinances change and many figures apply only in some cases, so check the cited section with the county before relying on one.

Common questions

What are the solar setbacks in Sweetwater County, WY?

The county's ordinance sets solar facilities back 50 ft from property lines, 200 ft (properties zoned agriculture) from roads and 100 ft (on all other lands allowed) from roads. Check the cited section with the county before relying on a figure.

How tall can a solar farm be in Sweetwater County, WY?

The ordinance sets a maximum height of 25 ft (Solar Energy Facility structures). Check the cited section with the county before relying on a figure.

What is the minimum lot size for a solar farm in Sweetwater County, WY?

The ordinance sets a minimum lot size of 40 acres. Check the cited section with the county before relying on a figure.