Lincoln County, Washington solar and wind ordinance

Solar: 60 ft from property lines, 20 ft maximum height. Wind: 1 × height (nonparticipating landowner) from property lines, 1,650 ft (whichever is greater) from homes, 1 × height (county roads) from roads. Every figure is quoted from the county's ordinance, read September 30, 2026.

Updated September 2026

Solar rules

2 figures read from the county's ordinance, each with the sentence it comes from.

Solar rules in the Lincoln County ordinance
Rule and what the ordinance saysRequirement
Property line setbackSetbacks for solar energy facilities shall meet a minimum setback of 60-feet from all property lines.60 ft
Maximum heightMaximum structure height for the solar array shall be 20-feet as measured from the highest existing native grade below each panel.20 ft

Source: Lincoln County ordinance (PDF), read September 30, 2026. Check the cited section with the county before relying on a figure.

Wind rules

6 figures read from the county's ordinance, each with the sentence it comes from.

Wind rules in the Lincoln County ordinance
Rule and what the ordinance saysRequirement
Property line setbacknonparticipating landownerThere shall be a minimum distance of one-times (1X) the height of the wind turbine generator plus one-hundred feet from the property line of any nonparticipating landowner .1 × height
Setback from homeswhichever is greaterSetbacks from existing residential structures shall be a minimum of one thousand six-hundred fifty feet or four-times (4X) the total extended height of the wind turbine, whichever is greater.1,650 ft
Setback from homeswhichever is greaterSetbacks from existing residential structures shall be a minimum of one thousand six-hundred fifty feet or four-times (4X) the total extended height of the wind turbine, whichever is greater.4 × height
Setback from homesnon-waivable setback to residencesThere shall be a non-waivable setback to residences of one-times (1X) tower height plus one-hundred feet.1 × height
Road setbackcounty roadsSetbacks from the rights-of-way of all county roads shall be the minimum distance of one-times (1X) the height of the wind turbine generator plus one-hundred feet .1 × height
Setback from boundaries of incorporated communitiesThere shall be a minimum setback distance of four-times (4X) the height of a turbine from the boundaries of incorporated communities.4 × height

Source: Lincoln County ordinance (PDF), read September 30, 2026. Check the cited section with the county before relying on a figure.

More on Lincoln County in Basepoint

  • Which zoning districts allow solar in Lincoln County
  • Property line and road setbacks drawn on any parcel in Lincoln County as its buildable area
  • Transmission, substations, parcels and environmental layers for the same site
Book a demo

Washington state law

State law can cap or override county rules. All Washington rules and counties.

State siting: Washington Energy Facility Site Evaluation Council (EFSEC)

Wind, solar and other alternative energy projects of any size, and storage facilities, may opt in to state certification by EFSEC instead of local permits; projects that do not opt in are permitted by the county.

RCW 80.50.060(1)(b) (as amended through 2026 c 244). Source

Limits on local rules

On the state route, the council can set aside local laws.

RCW 80.50.090, 80.50.100 (DOE and Berkeley Lab inventory, June 2024). Source

Wind standards in state law

Applies to projects EFSEC certifies, which must meet the state's environmental noise limits (set by land class: an industrial or farm source may reach 60 dBA at homes by day and 50 dBA at night); the same Ecology limits apply statewide to any noise source.

Wind standards set by Washington law
Noise60 dBA day, 50 dBA night (10 pm to 7 am) at homes from an industrial or farm-land source

WAC 463-62-030 (amended WSR 25-12-020, effective June 22, 2025), adopting WAC 173-60-040. Source

Solar standards in state law

Applies to projects EFSEC certifies, which must meet the state's environmental noise limits (set by land class: an industrial or farm source may reach 60 dBA at homes by day and 50 dBA at night); the same Ecology limits apply statewide to any noise source.

Solar standards set by Washington law
Noise60 dBA day, 50 dBA night (10 pm to 7 am) at homes from an industrial or farm-land source

WAC 463-62-030 (amended WSR 25-12-020, effective June 22, 2025), adopting WAC 173-60-040. Source

Every Washington figure in one spreadsheet

29 figures from 5 counties, each with its quote, source, date read and any condition. Plus the moratorium or ban on file and Washington state law.

CSV files that open in Excel or Google Sheets. No call required.

How these figures were read

We found Lincoln County's own ordinance and had two AI models read it separately. A figure is shown only when both read the same number and the sentence it comes from was found in the document. Moratoria and bans are checked against the adopting document. Ordinances change and many figures apply only in some cases, so check the cited section with the county before relying on one.

Common questions

What are the solar setbacks in Lincoln County, WA?

The county's ordinance sets solar facilities back 60 ft from property lines. Check the cited section with the county before relying on a figure.

How tall can a solar farm be in Lincoln County, WA?

The ordinance sets a maximum height of 20 ft. Check the cited section with the county before relying on a figure.

What are the wind turbine setbacks in Lincoln County, WA?

The county's ordinance sets wind turbines back 1,650 ft (whichever is greater) from homes, 4 × height (whichever is greater) from homes, 1 × height (non-waivable setback to residences) from homes, 1 × height (nonparticipating landowner) from property lines and 1 × height (county roads) from roads. Check the cited section with the county before relying on a figure.