Livingston Parish, Louisiana solar moratorium

Livingston Parish has a moratorium in force since May 23, 2024, running to November 23, 2026. It covers solar panel farms and commercial solar power plants.

Updated October 2026

Moratorium

Moratorium in force

Solar panel farms and commercial solar power plants

Adopted
May 23, 2024
Runs to
November 23, 2026
Scope
Residential rooftop solar not covered
Checked
October 8, 2026
Here we are up against the moratorium expiring at the end of October, and so much more has come to the forefront

Adopting document

More on Livingston Parish in Basepoint

  • Moratoria and local rules flagged on the parcels you screen
  • Transmission, substations, parcels and environmental layers for the same site
Book a demo

Louisiana state law

State law can cap or override county rules. All Louisiana rules and counties.

State siting: Louisiana Department of Conservation and Energy (formerly Department of Energy and Natural Resources)

Threshold is in acres, not MW: a solar facility of 75 acres or more needs a state permit, on top of parish rules.

La. R.S. 30:1142 to 30:1145 (Act 279 of 2025). Source

Every Louisiana figure in one spreadsheet

59 figures from 8 counties, each with its quote, source, date read and any condition. 1 of those places is not on this site. Plus the moratorium or ban on file and Louisiana state law.

CSV files that open in Excel or Google Sheets. No call required.

How these figures were read

Moratoria and bans are checked against the adopting document. Ordinances change and many figures apply only in some cases, so check the cited section with the county before relying on one.

Common questions

Is there a solar moratorium in Livingston Parish, LA?

Livingston Parish has a moratorium in force since May 23, 2024, running to November 23, 2026. It covers solar panel farms and commercial solar power plants. Checked against the adopting document on October 8, 2026.