Cerro Gordo County, Iowa solar, wind and battery storage ban

Cerro Gordo County has a ban in force since December 23, 2024. It covers Industrial and utility-scale wind, solar and battery storage prohibited on A-1 and A-2 land in unincorporated areas (Ordinance 69, replacing the 2023 moratorium).

Updated October 2026

Ban

Ban in force

Industrial and utility-scale wind, solar and battery storage prohibited on A-1 and A-2 land in unincorporated areas (Ordinance 69, replacing the 2023 moratorium)

Adopted
December 23, 2024
Runs to
No end date
Scope
Personal or on-site use such as rooftop solar on a home is not banned
Checked
October 8, 2026
the Cerro Gordo County Board of Supervisors early this afternoon approved an amendment to an ordinance that bans future large-scale industrial-grade development of wind turbines, solar energy or battery storage facilities in the rural portions of the county.

Adopting document

More on Cerro Gordo County in Basepoint

  • Moratoria and local rules flagged on the parcels you screen
  • Transmission, substations, parcels and environmental layers for the same site
Book a demo

Iowa state law

State law can cap or override county rules. All Iowa rules and counties.

State siting: Iowa Utilities Commission (formerly Iowa Utilities Board)

A plant of 25 MW or more needs a state certificate before construction.

Iowa Code 476A.1(5), 476A.2. Source

Limits on local rules

For plants of 25 MW or more, the state may issue its certificate even if the project does not meet county zoning; no limit was found for smaller projects.

Iowa Code 476A.5(3). Source

Every Iowa figure in one spreadsheet

114 figures from 17 counties, each with its quote, source, date read and any condition. 3 of those places are not on this site. Plus the 8 moratoria and bans on file and Iowa state law.

CSV files that open in Excel or Google Sheets. No call required.

How these figures were read

Moratoria and bans are checked against the adopting document. Ordinances change and many figures apply only in some cases, so check the cited section with the county before relying on one.

Common questions

Is there a solar, wind and battery storage ban in Cerro Gordo County, IA?

Cerro Gordo County has a ban in force since December 23, 2024. It covers Industrial and utility-scale wind, solar and battery storage prohibited on A-1 and A-2 land in unincorporated areas (Ordinance 69, replacing the 2023 moratorium). Checked against the adopting document on October 8, 2026.